# PPA, Article 12/6

- URL: https://procurelex.be/en/act/12-6 · Nederlands: https://procurelex.be/nl/wet/12-6
- Act of 17 June 2016 on public procurement, consolidated version in force from 2026-02-17; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/wet/2016/06/17/2016021053/justel
- Amended by: Ingevoegd bij W 2023-12-22/14, art. 3 (in force 01-01-2024)

Where an advance payment is granted and the public contract concerned is part of a project for which a permit is required, the contracting body may make the granting of the advance payment dependent on obtaining that permit, by means of a provision to that effect in the procurement documents.
For the purposes of Articles 12/1 to 12/5, a framework agreement is not regarded as a public contract, but a contract based on a framework agreement is regarded as a public contract.