# PPA, Article 87/1. Third-party rights over claims

- URL: https://procurelex.be/en/act/87-1 · Nederlands: https://procurelex.be/nl/wet/87-1
- Act of 17 June 2016 on public procurement, consolidated version in force from 2026-02-17; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/wet/2016/06/17/2016021053/justel
- Amended by: Ingevoegd bij W 2022-05-18/03, art. 8 (in force 09-06-2022); W 2023-12-22/14, art. 6 (in force 01-01-2024)

§ 1 The claims of the contractors arising from the performance of a public contract may not, until acceptance, be the subject of attachment, opposition, assignment or pledge.
Where the contract provides for a provisional and a final acceptance, the prohibition ends upon the provisional acceptance of the whole contract.
§ 2 With the exception of the advance payments referred to in Articles 12/1 to 12/8, these claims may be attached and may be the subject of opposition before the date of acceptance:
- by the workers and employees of the contractor, supplier or service provider up to the amount of their wages and salaries due for services performed within the framework of the contract in question;
- by the subcontractors and suppliers of the contractor, supplier or service provider, up to the amounts due to them for works, supplies or services which they have performed for the contract in question.
§ 3 With the exception of the advance payments referred to in Articles 12/1 to 12/8, the claims may likewise, before acceptance, be assigned or pledged by the contractor, supplier or service provider in favour of lenders, if they are used as security for credit or advances granted with a view to the performance of the contract in question, insofar as that credit or those advances are used at the same time as or after the notification of that assignment or pledge.
§ 4 The assignment and the pledge of the claim shall be notified to the contracting body by the assignee by bailiff's writ. The notification may also be made by registered letter sent by the assignee to the contracting body. To that end, the contracting body shall expressly indicate in the procurement documents the administrative details of the department to which the letter is to be addressed. To be valid, the notification must be made at the latest at the same time as the assignee's payment request.
The assignment of several claims may be notified by means of the same bailiff's writ or registered letter, provided that those claims relate to the same contracting body and arise from one and the same concluded public contract.
§ 5 The assignment and pledge shall take effect only after the workers, employees, subcontractors and suppliers who have levied a third-party attachment or lodged an opposition have been paid.
The sums arising therefrom may not be used by the lender, the assignee or the pledgee creditor to cover claims arising on any other ground against the contractor, before or during the performance of the financed works, supplies or services, as long as those works, supplies or services have not been accepted.
§ 6 The contracting body shall notify the assignees and pledgees of claims, by registered letter, of the third-party attachment or opposition which has been served on it at the request of the preferential creditors.