# PPA, Article 9. Lump-sum principle

- URL: https://procurelex.be/en/act/9 · Nederlands: https://procurelex.be/nl/wet/9
- Act of 17 June 2016 on public procurement, consolidated version in force from 2026-02-17; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/wet/2016/06/17/2016021053/justel

Public contracts shall be awarded on a lump-sum basis and without any material changes being capable of being made to them during their performance, subject to the exceptions to be determined by the King and in accordance with the conditions to be determined by Him.
However, public contracts may be awarded without a lump-sum price determination in the following cases:
   1° in exceptional cases, for works, supplies or services which are complex or which herald a new technique, involving significant technical risks, which make it necessary to start performing the services while not all the performance conditions and obligations can be fully determined;
   2° in extraordinary and unforeseeable circumstances, which could not have been foreseen by a diligent contracting body, where they relate to urgent works, supplies or services whose performance conditions are difficult to define.