# Award Decree, Article 32

- URL: https://procurelex.be/en/award-decree/32 · Nederlands: https://procurelex.be/nl/kb-plaatsing/32
- Royal Decree of 18 April 2017 on the award of public contracts in the classic sectors, consolidated version in force from 2026-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2017/04/18/2017020322/justel
- Amended by: KB 2018-04-15/01, art. 32 (in force 28-04-2018)

§ 1 Unless the procurement documents provide otherwise, the unit prices and lump-sum prices of public works contracts include all costs, measures and charges inherent in the performance of the contract, in particular:
   1° where applicable, the measures imposed by the regulations on the safety and health of employees in the performance of their work;
   2° all works and supplies necessary to prevent, and where applicable to remedy, landslides and other damage, such as shoring, sheet piling and dewatering;
   3° keeping intact and, where applicable, moving and replacing cables and pipes that may be encountered during earthworks, excavation or dredging works, insofar as the statutory duty to do so does not rest with the owners of those cables and pipes;
   4° the removal, within the limits of the earthworks, excavation or dredging works that may be necessary for the performance of the work:
      a) of soil, mud and gravel, stones, rubble stone, all kinds of rock, remains of masonry, turf, plantings, shrubs, stumps, roots, undergrowth, rubble and waste;
      b) of any boulder, irrespective of its volume, where the procurement documents state that the earthworks, excavation or dredging works are carried out in rocky terrain and, in the absence of such a statement, of any boulder, masonry block or concrete block consisting of a single piece whose volume does not exceed half a cubic metre;
   5° the transport and removal of excavated material either outside the domain of the contracting authority, or to the places for reuse within the limits of the construction sites, or to the dumping sites provided for in the procurement documents;
   6° all general, additional and maintenance costs during the performance period and the guarantee period.
Also included in the price of the contract are all activities that by their nature depend on or are connected with those described in the procurement documents.
§ 2 Unless the procurement documents provide otherwise, the unit prices and lump-sum prices of public supply contracts include all costs, measures and charges inherent in the performance of the contract, in particular:
   1° packaging, except where it remains the property of the tenderer, and loading, transshipment, reloading, transport, insurance and customs clearance;
   2° unloading, unpacking and stacking at the place of delivery, provided that the procurement documents state the exact place of delivery and the means of access;
   3° the documentation relating to the supply;
   4° assembly and making ready for operation;
   5° the training necessary for use.
§ 3 Unless the procurement documents provide otherwise, the unit prices and lump-sum prices of public service contracts include all costs, measures and charges inherent in the performance of the contract, in particular:
   1° administration and secretarial work;
   2° travel, transport and insurance;
   3° the documentation relating to the services;
   4° the supply of documents or items inherent in the performance;
   5° packaging;
   6° the training necessary for use;
   7° where applicable, the measures imposed by the legislation on the safety and health of employees for the performance of their work.
