# Award Decree, Article 36

- URL: https://procurelex.be/en/award-decree/36 · Nederlands: https://procurelex.be/nl/kb-plaatsing/36
- Royal Decree of 18 April 2017 on the award of public contracts in the classic sectors, consolidated version in force from 2026-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2017/04/18/2017020322/justel

§ 1 If the price or cost examination in accordance with Article 35 shows that prices or costs are offered that appear abnormally low or high, the contracting authority conducts an inquiry of the latter. Where use is made of the competitive procedure with negotiation, the simplified negotiated procedure with prior publication and the negotiated procedure without prior publication, the inquiry is conducted on the most recently submitted tenders. This does not prevent the contracting authority from already conducting this inquiry at an earlier stage of the procedure.
§ 2 In the price or cost inquiry, the contracting authority requests the tenderer to provide the necessary written justification of the composition of the price or cost regarded as abnormal within a period of twelve days, unless the invitation provides for a longer period. Where, however, use is made of the negotiated procedure without prior publication, the contracting authority may, by an expressly reasoned provision in the procurement documents, provide for a shorter period.
The tenderer bears the burden of proving the dispatch of the justification.
The justification relates in particular to:
   1° the efficiency of the construction process, of the production process of the products or of the provision of the services;
   2° the technical solutions chosen or the exceptionally favourable conditions available to the tenderer for the execution of the works, the supply of the products or the provision of the services;
   3° the originality of the works, products or services offered by the tenderer;
   4° the possible receipt by the tenderer of lawfully granted State aid.
In the context of the price or cost inquiry referred to in the first paragraph, the contracting authority requests the tenderer to submit written justifications regarding compliance with the obligations referred to in Article 7, first paragraph, of the Act, which apply in the fields of social, labour and environmental law, including the obligations that apply in the field of well-being, wages and social security.
The contracting authority is not, however, required to request justifications for prices for negligible items.
Where necessary, the contracting authority questions the tenderer again. This is done in writing. In that case the period of twelve days may be shortened.
§ 3 The contracting authority assesses the justifications received and:
   1° either finds that the amount of one or more non-negligible items is abnormal in nature and rejects the tender because of the substantial irregularity affecting it;
   2° or finds that the total tender amount is abnormal in nature and rejects the tender because of the substantial irregularity affecting it;
   3° or states in the award decision its reasons for finding that the total tender amount is not abnormal in nature.
The contracting authority also rejects the tender where it has found that the total tender amount is abnormally low because the tender does not comply with the obligations in the field of environmental, social or labour law referred to in Article 7, first paragraph, of the Act, because of the substantial irregularity affecting it. Where the tender does not comply with the obligations in the field of federal social or labour law, the contracting authority communicates this in accordance with § 5, second paragraph.
In the context of the assessment, the contracting authority may also take into account information that does not originate from the tenderer. This information is submitted to the tenderer in order to give it the opportunity to respond to it.
Where a contracting authority finds that a tender appears to be abnormally low as a result of State aid obtained by the tenderer, the tender may be rejected on that ground alone only after consultation with the tenderer and where the latter is unable to demonstrate, within a sufficient time limit set by the contracting authority, that the aid in question is compatible with the internal market, within the meaning of Article 107 of the Treaty on the Functioning of the European Union. Where the contracting authority rejects a tender in such a situation, it communicates this in accordance with § 5, third paragraph. This paragraph applies only to contracts whose estimated amount is equal to or higher than the thresholds for European publication.
§ 4 Where, in a public works contract or a service contract in a fraud-sensitive sector, awarded by open or restricted procedure, the most economically advantageous tender is evaluated solely on the basis of price, and insofar as at least four tenders have been taken into consideration in accordance with the third and fourth paragraphs, the contracting authority conducts a price or cost inquiry in accordance with §§ 2 and 3, for each tender whose total tender amount is at least fifteen per cent below the average amount of the tenders submitted by the tenderers. The same applies to public works contracts and to service contracts in a fraud-sensitive sector, awarded by open or restricted procedure, where the most economically advantageous tender is evaluated on the basis of the best price-quality ratio, with the price criterion accounting for at least fifty per cent of the total weighting of the award criteria. In the latter case, however, the contracting authority may provide in the procurement documents for a percentage higher than fifteen per cent.
The average of the amounts is calculated as follows:
   1° if the number of tenders is equal to or greater than seven, by excluding both the lowest tender and the highest tenders which together form a quarter of the number of tenders submitted. If this number is not divisible by four, the quarter is rounded up to the next whole number;
   2° if the number of tenders is lower than seven, by excluding the lowest and the highest tender.
The calculation of the average of the amounts is based on all the tenders of the selected tenderers. As regards the open procedure, this calculation may also be based on the tenders of the provisionally selected tenderers in accordance with Article 75.
In the context of this calculation, the contracting authority may, however, decide not to take into account the manifestly irregular tenders.
The procurement documents may make this paragraph applicable to public supply contracts or to contracts for services other than those referred to in Article 2, 13°, awarded by open or restricted procedure and in which the most economically advantageous tender is evaluated solely on the basis of price.
§ 5 Where, in the context of a public works, supply or service contract, the tender is rejected on the basis of an abnormal price or cost, the contracting authority communicates this without delay to the Auditor-General of the Belgian Competition Authority. This communication contains at least the following information: the identification details of the tenderers concerned, the subject matter of the contract, as well as the abnormally high or low price or cost.
Where, in the context of a public works, supply or service contract, the tender is rejected on the ground that it has been found to be abnormally low because it does not comply with the obligations in the field of federal social or labour law referred to in Article 7, first paragraph, of the Act, the contracting authority communicates this without delay to the Social Intelligence and Investigation Service (Sociale inlichtingen- en opsporingsdienst), stating the information referred to in the first paragraph.
Where, in the context of a public works, supply or service contract, the tender is rejected on the ground that it has been found to be abnormally low as a result of State aid that is not compatible with the internal market, the contracting authority notifies the European Commission of this without delay. A copy of this notification is also forwarded without delay to the contact point referred to in Article 163, § 2, of the Act.
Where a tender in the context of a public works contract is rejected on the basis of an abnormally low price or cost, the Contractors' Accreditation Commission is also informed of this without delay.
§ 6 Unless the procurement documents provide otherwise, this Article does not apply to the competitive procedure with negotiation, nor to the simplified negotiated procedure with prior publication, nor to the negotiated procedure without prior publication, insofar as it concerns a supply or service contract whose estimated value is lower than the thresholds for European publication or a public works contract whose estimated value is lower than EUR 500,000.