# Award Decree, Article 86

- URL: https://procurelex.be/en/award-decree/86 · Nederlands: https://procurelex.be/nl/kb-plaatsing/86
- Royal Decree of 18 April 2017 on the award of public contracts in the classic sectors, consolidated version in force from 2026-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2017/04/18/2017020322/justel

§ 1 Where a tenderer has, in accordance with Articles 34 and 79, § 2, corrected the quantity of one or more items of the summary bill of quantities or inventory, the contracting authority shall check those changes, correct them if necessary according to its own calculations and, where applicable, amend the bills of quantities or inventories attached to the tenders.
For the tenderer that has proposed a reduction pursuant to Article 79, § 2, 2°, the total price corresponding to the quantity thus reduced shall become a lump-sum price, on condition and to the extent that the contracting authority accepts this correction.
Where the contracting authority cannot check the changes to an item with estimated quantities by its own calculations, it shall reduce the proposed increase or decrease of the quantity to the original quantity of the bill of quantities or inventory.
§ 2 Where a tenderer has not stated a price for any item of the summary bill of quantities or the inventory, the contracting authority may either reject the tender as irregular or retain it by filling the omission using the following formula:
P = L x Y
X
where the following is to be understood by:
- P: the price of the item for which the tenderer has not stated a price;
- L: the value obtained on the basis of the arithmetic mean of the price, where applicable corrected by the contracting authority in accordance with Article 34 and paragraph 1 of this Article, indicated for that item by the tenderers that stated the price in their summary bill of quantities or inventory;
- Y: the total amount of the bill of quantities or inventory of the tenderer that has not stated a price for the item concerned, possibly corrected on the basis of the quantities found to be correct for each item of the bill of quantities or inventory and in accordance with Article 34 and paragraph 1 of this Article;
- X: the value obtained on the basis of the arithmetic mean of the total amount of the bill of quantities or inventory of all tenderers that have stated the price for the item concerned, possibly corrected on the basis of the quantities found to be correct for each item of the bill of quantities or inventory and in accordance with Article 34 and paragraph 1 of this Article, without taking into account the price indicated for that item.
If the tenderer has not stated a price for several items, the price that the other tenderers have stated for those items shall not be taken into account in calculating the value of X.
For the calculation of the values L and X, the contracting authority may decide not to take into account the tenders that state an abnormal price for the item concerned.
§ 3 Whenever, pursuant to Article 79, § 2, an omission in the summary bill of quantities or in the inventory has been filled, the contracting authority shall proceed as follows:
   1° it shall examine the merits of that addition and correct it if necessary according to its own findings.
If the other tenderers have not proposed prices for these omissions, these prices shall, for each item, with a view to the ranking of the tenders, be calculated according to the formula below and shall be retained in the final correction of the tenders:
S = L x Y
X
where the following is to be understood by:
- S: the price of the omission;
- L: the amount, possibly corrected by the contracting authority, for the omission in the summary bill of quantities or the inventory of the tenderer that pointed out the omission;
- X: the total tender amount of the same tenderer, where applicable corrected on the basis of the quantities found to be correct for each item of the summary bill of quantities or inventory and in accordance with Article 34 and paragraph 1 of this Article, without taking the omissions into account;
- Y: the total tender amount of the tenderer concerned that has not stated the omission, possibly corrected on the basis of the quantities found to be correct for each item of the summary bill of quantities or the inventory and in accordance with Article 34 and paragraph 1 of this Article, without taking the omission into account;
   2° where several tenderers have stated the same omission, L and X in the aforementioned formula shall be obtained by taking the arithmetic mean of the values L and X in the summary bill of quantities or inventory of those tenderers;
   3° in the cases referred to in 1° and 2°, the unit price of the omission shall be obtained by dividing the amount S by the corresponding quantity, as possibly corrected by the contracting authority;
   4° for the calculation of the prices of an omission in accordance with 1° and 2°, the contracting authority may decide not to take into account the tender in which an abnormal price has been offered for that omitted item.
If no tenderer has offered a normal price for that omission, the contracting authority may award the contract without that item.
§ 4 Only for the ranking of the tenders shall the quantities accepted by the contracting authority that are greater than or equal to the quantities of the original bill of quantities or inventory be entered, without distinction, in all bills of quantities or inventories.
On the other hand, the changes accepted by the contracting authority that result in a reduction of the quantities shall operate only in favour of the tenderers that reported them and only to the extent that their justification has been accepted. Thus:
   1° if the quantity proposed by the tenderer is smaller than the quantity accepted by the contracting authority, the latter quantity shall be entered in the bill of quantities or inventory;
   2° if the quantity proposed by the tenderer lies between the quantity accepted by the contracting authority and the quantity of the original bill of quantities or inventory, the quantity proposed by the tenderer shall be entered in the bill of quantities or inventory;
   3° if the quantity proposed by the tenderer is greater than the quantity of the original bill of quantities or inventory, the quantity proposed by the tenderer shall be reduced to the quantity of the original bill of quantities or inventory.
§ 5 For the application of this Article, the contracting authority shall take into account the corrections proposed in regular or irregular tenders submitted by selected or provisionally selected tenderers in accordance with Article 66, § 2, of the Act.