# Thresholds and estimated value

- URL: https://procurelex.be/en/faq/thresholds-and-estimated-value
- Updated 2026-11-22
- Draft – awaiting legal review
- Legal basis: Article 16, Article 16, second paragraph, Article 92

How the value of a contract is estimated, and which amounts decide which rules apply.

Short answers on estimating the value of a contract. Each answer cites the article it rests on; the [guide on thresholds and estimated value](https://procurelex.be/en/guides/thresholds-and-estimated-value) goes further.

## Is the estimated value with or without VAT?

Without VAT: every amount in the Act is, unless otherwise provided, an amount net of value added tax ([Article 16, second paragraph](https://procurelex.be/en/act/16#pl2)), and the estimate is the total amount payable net of VAT ([Award Decree, Article 7, § 1](https://procurelex.be/en/award-decree/7#p1)).
## Do options and extensions count?

Yes. The estimate takes into account all options, lots, repetitions, fixed and conditional parts, prizes, revision clauses and extensions ([Award Decree, Article 7, § 1](https://procurelex.be/en/award-decree/7#p1)).
## May a contract be split to stay below a threshold?

No, unless objective reasons justify it. Nor may the method of calculation be chosen to take the contract outside the publication rules ([Award Decree, Article 7, § 3](https://procurelex.be/en/award-decree/7#p3)).
## What are the European thresholds?

EUR 5,404,000 for works; EUR 140,000 for supplies and services of the federal contracting authorities of Annex 2, Part A; EUR 216,000 for those of the other contracting authorities; EUR 750,000 for social and other specific services ([Award Decree, Article 11](https://procurelex.be/en/award-decree/11)). The [thresholds](https://procurelex.be/en/thresholds) page gives them with their source.
## Which moment counts for the estimate?

The moment the contract notice is sent or, where there is no notice, when the procedure begins ([Award Decree, Article 7, § 4](https://procurelex.be/en/award-decree/7#p4)). The estimate at the start decides the rules for the whole procedure ([Award Decree, Article 6](https://procurelex.be/en/award-decree/6)).