Where a contract is published, when communication must be electronic, what an electronic platform must guarantee and how the procurement documents are made available.

A public contract is now awarded electronically from start to finish: the notice, the procurement documents, the questions, the tenders. This is what the Act and the Award Decree lay down about it.

## Publication

The contracting authority publishes its contracts and framework agreements by a contract notice, except in the negotiated procedure without prior publication, for contracts based on a framework agreement and in the other cases of [Article 61](https://procurelex.be/en/act/61).

| Contract                      | Where it is published                                                  | Basis            |
| ----------------------------- | ---------------------------------------------------------------------- | ---------------- |
| From the European thresholds  | Official Journal of the European Union and Bulletin der Aanbestedingen | [Award Decree, Article 8, § 1](https://procurelex.be/en/award-decree/8#p1)    |
| Below the European thresholds | Bulletin der Aanbestedingen; voluntarily also in the Official Journal  | [Award Decree, Article 8, § 1, third paragraph](https://procurelex.be/en/award-decree/8#p1-l3) |

The notice in the Bulletin der Aanbestedingen (the Belgian Bulletin of Tenders) may not differ in content from the one in the Official Journal, and may not appear earlier, unless the contracting authority has not been informed of the European publication within two days of the confirmation of receipt ([Award Decree, Article 8, § 1, second paragraph](https://procurelex.be/en/award-decree/8#p1-l2)). Only those notices count as official publication; no other publication may precede them or differ from them in content ([Award Decree, Article 8, § 2](https://procurelex.be/en/award-decree/8#p2), [Award Decree, Article 8, § 2, second paragraph](https://procurelex.be/en/award-decree/8#p2-l2)). Notices use the electronic standard forms of the FPS Policy and Support ([Award Decree, Article 8, § 3](https://procurelex.be/en/award-decree/8#p3)), and publication is made by electronic means ([Award Decree, Article 8, § 4](https://procurelex.be/en/award-decree/8#p4)).

## Electronic communication

Communication and information exchange between the contracting authority and economic operators, including the electronic submission of tenders, take place at every stage by electronic means ([Article 14, § 1](https://procurelex.be/en/act/14#p1)). Those means must be non-discriminatory, generally available and interoperable ([Article 14, § 1, second paragraph](https://procurelex.be/en/act/14#p1-l2)). There are exceptions for specialised file formats or equipment and for physical models ([Article 14, § 2](https://procurelex.be/en/act/14#p2)), and for security or the particularly sensitive nature of information ([Article 14, § 3](https://procurelex.be/en/act/14#p3)); the contracting authority then states the reasons ([Article 14, § 2, second paragraph](https://procurelex.be/en/act/14#p2-l2)).

Oral communication is allowed, if sufficiently documented, but not for the essential elements: the procurement documents, the requests to participate and the tenders ([Article 14, § 4](https://procurelex.be/en/act/14#p4)).

## The electronic platform

The contracting authority ensures the integrity of the data and the confidentiality of the tenders, and examines their content only after the time limit for submission ([Article 14, § 6](https://procurelex.be/en/act/14#p6)). The electronic platform that receives tenders and requests must, among other things, record the exact time of receipt, prevent access before the deadline, give access only to authorised persons and make breaches detectable ([Article 14, § 7](https://procurelex.be/en/act/14#p7)).

In the open procedure and the simplified negotiated procedure the tenderer need not sign the tender and its annexes one by one: they are signed globally on the submission report ([Award Decree, Article 42, § 1](https://procurelex.be/en/award-decree/42#p1)). Where the platform is unavailable, the deadline may be postponed ([Award Decree, Article 57, § 1](https://procurelex.be/en/award-decree/57#p1)).

## The procurement documents

From the publication of the notice the contracting authority offers unrestricted, full, direct and free electronic access to the procurement documents; the notice gives the internet address ([Article 64, § 1](https://procurelex.be/en/act/64#p1)). Where that is not possible, the time limit for tenders is extended by five days ([Article 64, § 1, third paragraph](https://procurelex.be/en/act/64#p1-l3)). Additional information is provided, if requested in good time, no later than six days before the time limit for the receipt of tenders ([Article 64, § 2](https://procurelex.be/en/act/64#p2)).

Electronic submission also saves time: in the open and the restricted procedure the time limit for tenders may then be five days shorter ([Article 36, § 4](https://procurelex.be/en/act/36#p4), [Article 37, § 5](https://procurelex.be/en/act/37#p5)). See the guide on [time limits](https://procurelex.be/en/guides/time-limits-for-tenders).

## Below EUR 30,000

Article 14 does not apply to contracts of limited value ([Article 92, 1°](https://procurelex.be/en/act/92#p1o)): the obligation to communicate electronically falls away there.