# Performance Decree, Article 116. Delivery period

- URL: https://procurelex.be/en/performance-decree/116 · Nederlands: https://procurelex.be/nl/kb-uitvoering/116
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel

§ 1 The delivery period is set either in working days or in days, weeks or months, or else from date to date.
Where the period is set in working days, the following are not regarded as such:
   1° Saturdays, Sundays and public holidays;
   2° paid annual leave days and compensatory rest days determined in a Royal Decree or in a collective labour agreement made generally binding by Royal Decree.
Where the delivery period is set in days, weeks or months, the closing days for annual holidays in the supplier's undertaking are not counted, unless the period constituted an award criterion of the contract.
§ 2 The delivery period begins, as the case may be, either on the day following the date on which the contract was concluded, or on the day of the order.
The delivery period includes the time needed for the operations preceding production and for the preparation of the deliveries, in particular any preliminary inspections.