# Performance Decree, Article 12/2

- URL: https://procurelex.be/en/performance-decree/12-2 · Nederlands: https://procurelex.be/nl/kb-uitvoering/12-2
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: Ingevoegd bij KB 2017-06-22/01, art. 13 (in force 30-06-2017); KB 2018-04-15/01, art. 8 (in force 28-04-2018)

§ 1 The contracting authority may verify whether grounds for exclusion as referred to in Articles 67 to 69 of the Act or in Article 63 of the royal decree for defence and security exist in respect of the direct subcontractor(s) of the contractor. The contracting authority requests that the contractor proceed to replace the subcontractor(s) in respect of whom one of the exclusion grounds referred to in Articles 67 and 68 of the Act or in Article 63, § 1, of the royal decree for defence and security has come to light in the investigation. Where it concerns an optional exclusion ground as referred to in Article 69 of the Act or in Article 63, § 2, of the royal decree for defence and security, the contracting authority may do the same and the contractor is then bound to do the same.
By way of derogation from the first paragraph, where it concerns a contract in a fraud-prone sector whose estimated value is equal to or higher than the thresholds for European publication, the contracting authority is required, as soon as the data referred to in Article 12/1 have been provided to it, to proceed without delay to the investigation referred to in the first paragraph.
A report is drawn up of the finding, referred to in the first paragraph, of the existence of an exclusion ground and of the request for replacement, and is sent to the contractor in accordance with Article 44, § 2, first paragraph. The latter has a period of fifteen days following the date of dispatch of the aforementioned report to demonstrate that the subcontractor concerned has been replaced. During this period, evidence may still be provided that the tax or social debts have been regularised. The corrective measures referred to in the third paragraph may likewise still be taken during the aforementioned period of fifteen days, unless the procurement documents require that the data on the subcontractors be provided in the form of the ESPD in accordance with Article 12/1, fourth paragraph, in which case the corrective measures are already included in the ESPD.
The period of fifteen days referred to in the third paragraph may be shortened in accordance with Article 44, § 2, third paragraph.
§ 2 The contracting authority may verify whether grounds for exclusion as referred to in paragraph 1, first paragraph, exist in respect of a subcontractor further down the subcontracting chain. The contracting authority requests that the contractor take the necessary measures to provide for, or have provided for, the replacement of the subcontractor in respect of whom an exclusion ground as referred to in Articles 67 and 68 of the Act or in Article 63, § 1, of the royal decree for defence and security has come to light in the investigation. Where it concerns an optional exclusion ground as referred to in Article 69 of the Act or in Article 63, § 2, of the royal decree for defence and security, the contracting authority may do the same and the contractor is bound to do the same.
A report is drawn up of the finding, referred to in the first paragraph, of the existence of an exclusion ground and of the request for replacement, and is sent to the contractor in accordance with Article 44, § 2, first paragraph. The latter has a period of fifteen days following the date of dispatch of this report to demonstrate that the subcontractor concerned has been replaced. During the aforementioned period of fifteen days, the corrective measures referred to in the third paragraph may still be taken and evidence may still be provided that the tax and social debts have been regularised.
§ 3 This Article does not affect the possibility for the subcontractor that is in a situation of exclusion to prove that the measures it has taken are sufficient to demonstrate its reliability, despite the applicable exclusion ground.
The subcontractor referred to in the first paragraph has the possibility of still putting its affairs in order as regards social and tax debts. In the course of the performance, this possibility may be used only once.
This paragraph does not apply to contracts falling within the scope of the Defence and Security Act.
§ 4 Without prejudice to the possibility of applying ex officio measures, any infringement of the obligation of replacement referred to in the first paragraph or of the obligation referred to in the second paragraph to take the necessary measures to provide for the replacement gives rise to the application of a penalty that is daily and amounts to 0.2 per cent of the original contract amount. This penalty is applied from the fifteenth day after the date of dispatch of the registered mail or the electronic mail that likewise guarantees the exact date of dispatch, referred to in Article 44, § 2, and runs up to and including the day on which the infringement has been brought to an end.
The penalty referred to in the first paragraph may, however, never exceed:
   a) EUR 5,000 per day where it concerns a contract whose original contract price is lower than EUR 10,000,000;
   b) EUR 10,000 per day where it concerns a contract whose original contract amount is equal to or higher than EUR 10,000,000.