# Performance Decree, Article 121. Modifications to the contract

- URL: https://procurelex.be/en/performance-decree/121 · Nederlands: https://procurelex.be/nl/kb-uitvoering/121
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2014-02-07/10, art. 76 (in force 03-03-2014); KB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21); KB 2017-06-22/01, art. 2 (in force 30-06-2017)

§ 1 Every order to modify the contract is given in writing. An oral order is, however, treated as equivalent to a written order if the supplier has reported it to the supervising official within forty-eight hours by registered mail or by electronic means that guarantee the exact date of dispatch in a comparable manner, and if the contracting body has not refuted it within three working days of receipt of that letter.
The orders indicate the modifications that must be made to the original provisions of the contract.
§ 2 Unforeseen deliveries that the supplier has to carry out, foreseen deliveries that are omitted and all other modifications are calculated at the unit prices of the tender or, if none are set, at unit prices to be agreed.
§ 3 Every modification of the contract price takes place by consultation between the parties on the basis of a proposal submitted by the supplier by registered mail or by electronic means that guarantee the exact date of dispatch in a comparable manner, within a period of thirty days from the date on which the modification orders were validly given.
If no agreement is reached on the new unit prices, the contracting body sets them of its own motion, without prejudice to all rights of the supplier.
The supplier continues the deliveries without interruption, despite any disputes to which the setting of new prices may give rise.
§ 4 In the event of additional deliveries or modifications to the foreseen deliveries, the written order, the adjustment statement or the additional deed states:
   1° either the extension of the performance period on the basis of the increase in the amount of the contract and the nature of the modifications and the additional deliveries;
   2° or the exclusion of any extension of the period.
§ 5 In the case of fixed or minimum quantities to be supplied, and where the modifications ordered by the contracting body lead to one or more adjustments which together cause a reduction of the fixed or minimum quantities, the supplier is entitled to a lump-sum compensation of ten per cent of that reduction, irrespective of the final amount of the contract.
