# Performance Decree, Article 123. Penalties for delay

- URL: https://procurelex.be/en/performance-decree/123 · Nederlands: https://procurelex.be/nl/kb-uitvoering/123
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2017-06-22/01, art. 2 (in force 30-06-2017); KB 2017-06-22/01, art. 44 (in force 30-06-2017)

§ 1 Penalties for delay are calculated at the rate of 0.1 per cent per day of delay, with a maximum of seven and a half per cent, of the value of the deliveries made with the same delay.
Where the delivery period constitutes an award criterion of the contract, the procurement documents determine the method of calculating the penalties for delay for the deliveries made with the same delay. In that case the procurement documents may increase the above-mentioned percentage to a maximum of ten per cent. This percentage is set in proportion to the relative importance of the award criterion relating to the performance period. If the method of calculation is not stated in the procurement documents, that of the first paragraph applies.
The value of the deliveries is calculated on the basis of the original contract amount, taking account of the modifications made but not of the price revisions referred to in Article 38/7, § 2, and of the reductions for loss of value referred to in Article 71 of this Decree.
Penalties for delay whose total amount does not reach seventy-five euro per contract are not charged.
The date on which the deliveries are made available to the contracting body for the purpose of partial provisional acceptance applies as the date of delivery for the application of any penalties for delay.
§ 2 Where the contract consists of several parts or phases, each with its own performance period and its own amount, each of the parts is treated as a separate contract for the application of the penalties.
If the contract does not consist of parts or phases within the meaning of the first paragraph, but the procurement documents set partial performance periods without designating them as binding, those periods must be regarded as mere forecasts for the performance of the contract and, for the application of the penalties, only the final period is taken into account. If, on the other hand, the procurement documents state that the partial performance periods are mandatory, failure to observe them is penalised by special penalties provided for that purpose in those documents or, if there is no such provision, by penalties calculated in accordance with the first paragraph.