# Performance Decree, Article 130. Double provisional acceptance

- URL: https://procurelex.be/en/performance-decree/130 · Nederlands: https://procurelex.be/nl/kb-uitvoering/130
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2017-06-22/01, art. 2 (in force 30-06-2017)

§ 1 Each partial provisional acceptance at the place of production must be requested in writing from the contracting body by the supplier.
§ 2 The date on which the deliveries are made available for the operations of partial provisional acceptance is set by the supplier in the request for acceptance. If, however, the date is not stated or if it is earlier than the date on which the request for acceptance reaches the contracting body, it is the latter date that is taken into account for presenting the deliveries for acceptance.
§ 3 For the notification of approval or refusal, the contracting body has the following periods, beginning on the day of receipt of the request to proceed with the inspection:
   1° thirty days;
   2° sixty days if the acceptance operations take place in a laboratory.
The procurement documents may, however, set shorter periods.
The period available to the contracting body for announcing its decision is extended by the number of days needed for the outward and return journey of the inspectors.
In the event of refusal of the deliveries presented for acceptance, the number of days by which the aforementioned periods are exceeded is taken into account in establishing any delay in the replacement deliveries made.
§ 4 Provisional acceptance is complete only after the contracting body has carried out the acts referred to in Article 120.