# Performance Decree, Article 15

- URL: https://procurelex.be/en/performance-decree/15 · Nederlands: https://procurelex.be/nl/kb-uitvoering/15
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2017-06-22/01, art. 2 (in force 30-06-2017)

The contractor that has recourse to a subcontractor shall communicate the payment conditions applicable to the contract to that subcontractor when concluding the agreement with the latter. The subcontractor has the right to rely on those payment conditions against the contractor in order to claim from it payment of the sums owed for the works, supplies and services in performance of the contract.
For the purposes of the first paragraph, the subcontractor is regarded as the contractor and the contractor as the contracting body in relation to the former's own subcontractors.