# Performance Decree, Article 36. Detail and working drawings drawn up by the contractor

- URL: https://procurelex.be/en/performance-decree/36 · Nederlands: https://procurelex.be/nl/kb-uitvoering/36
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2017-06-22/01, art. 2 (in force 30-06-2017)

The contractor shall draw up at its own expense all detail and working drawings that it needs in order to bring the performance of the contract to a successful conclusion.
The procurement documents specify which drawings are approved by the contracting body. The latter has a period of thirty days, counting from the date on which the drawings were submitted, to approve or reject them.
Any corrected drawings are submitted again to the contracting body, which has a period of fifteen days to approve them, in so far as the corrections requested are not the result of new requirements from the contracting body.
Any overrun of the periods stated in the second and third paragraphs gives rise to a proportionate extension of the performance period, unless the contracting body proves that the delay actually caused to the detriment of the contractor is of shorter duration than the overrun of the period.
The procurement documents state the number of copies of the drawings that the contractor must hand over to the contracting body.
The contracting body may not reproduce these drawings. They may be used only for the purposes of the contract and not for any other purpose.
The above provisions also apply to the other documents and objects that the contractor draws up or produces in order to bring the contract to a successful conclusion.