# Performance Decree, Article 38/11. Acts of the contracting body and of the contractor

- URL: https://procurelex.be/en/performance-decree/38-11 · Nederlands: https://procurelex.be/nl/kb-uitvoering/38-11
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: Ingevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)

The procurement documents shall provide for a revision clause, as laid down in Article 38, in which the arrangements are determined for the revision of the conditions of the contract where the contracting body or the contractor has suffered a delay or a detriment as a result of negligence, delays or any acts whatsoever that can be attributed to the other party.
The revision referred to in the first paragraph may consist of one or more of the following measures:
   1° the adjustment of the contractual provisions, including the extension or shortening of the performance periods;
   2° damages;
   3° termination of the contract.
Where the procurement documents do not contain a revision clause as referred to in the first paragraph, the arrangement contained in the second paragraph is deemed to apply by operation of law.