# Performance Decree, Article 38/12. Compensation for suspensions ordered by the contracting body and incidents during performance

- URL: https://procurelex.be/en/performance-decree/38-12 · Nederlands: https://procurelex.be/nl/kb-uitvoering/38-12
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: Ingevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017); KB 2018-04-15/01, art. 11 (in force 28-04-2018)

§ 1 The procurement documents shall provide for a revision clause, as laid down in Article 38, clarifying that the contractor is entitled to damages for suspensions ordered by the contracting body under the following cumulative conditions:
   1° the suspension exceeds in total one twentieth of the performance period and at least ten working days or fifteen calendar days, depending on whether the performance period is expressed in working days or calendar days;
   2° the suspension is not the result of adverse weather conditions or of other circumstances external to the contracting body because of which the contract, in the opinion of the contracting body, cannot be continued without difficulty at that time;
   3° the suspension takes place within the performance period of the contract.
Where the procurement documents do not contain a revision clause as referred to in the first paragraph, the arrangement contained in the aforementioned paragraph is deemed to apply by operation of law.
§ 2 The contracting body may provide for a revision clause, as laid down in Article 38, in which it reserves the right to suspend the performance of the contract for a certain period, in particular because in its opinion the contract cannot be performed without difficulty at that time.
Where applicable, the performance period is extended by the delay caused by the suspension, on condition that the contractual period has not expired. Where that period has expired, a refund of the fine for delay in performance may be granted in accordance with Article 50.
Where the services are suspended on the basis of a revision clause referred to in this paragraph, the contractor must take, at its own expense, all necessary precautionary measures in order to protect the services already performed and the materials against possible damage caused by adverse weather conditions, theft or other malicious acts.
