# Performance Decree, Article 38/15

- URL: https://procurelex.be/en/performance-decree/38-15 · Nederlands: https://procurelex.be/nl/kb-uitvoering/38-15
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: Ingevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)

The contractor may rely on the application of one of the revision clauses referred to in Articles 38/9 to 38/11 only if he briefly notifies the contracting body of the influence of the facts or circumstances invoked on the progress and the cost price of the contract. This notification must be made in writing, on pain of forfeiture, within the period stated in Article 38/14. The aforementioned obligations apply regardless of whether the contracting body is aware of the facts or circumstances.
The contractor's request invoking the application of one of the revision clauses referred to in Articles 38/9 and 38/11 is inadmissible if the request is based on facts or circumstances that were not made known to the contracting body by the contractor in good time and whose existence and influence on the contract it has consequently been unable to verify in order to take the measures possibly required by the situation.
As regards written orders of the contracting body, including those referred to in Article 80, § 1, the contractor is obliged to inform the contracting body only as soon as he knows or ought to know the influence that the orders could have on the progress and the cost price of the contract.