# Performance Decree, Article 38/16

- URL: https://procurelex.be/en/performance-decree/38-16 · Nederlands: https://procurelex.be/nl/kb-uitvoering/38-16
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: Ingevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)

The contractor requesting the application of one of the revision clauses referred to in Articles 38/8 to 38/9, 38/11 and 38/12 must, on pain of forfeiture, submit the itemised justification of his request in writing to the contracting body within the following periods:
   1° before the expiry of the contractual periods, in order to obtain an extension of the period or the termination of the contract;
   2° no later than ninety days following the date of notification to the contractor of the report of provisional acceptance of the contract, in order to obtain a revision of the contract other than that referred to in 1° or damages;
   3° no later than ninety days after the expiry of the guarantee period, in order to obtain a revision of the contract other than that referred to in 1° or damages, where this request for application of the revision clause originates in facts or circumstances that occurred during the guarantee period.