# Performance Decree, Article 38/2. Unforeseeable circumstances on the part of the contracting body

- URL: https://procurelex.be/en/performance-decree/38-2 · Nederlands: https://procurelex.be/nl/kb-uitvoering/38-2
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: Ingevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)

A modification may be made to a contract without a new award procedure where each of the following conditions is met:
   1° the modification is the necessary consequence of circumstances that a diligent contracting body could not foresee;
   2° the modification does not change the overall nature of the contract or framework agreement;
   3° the price increase resulting from a modification does not exceed fifty per cent of the value of the original contract or framework agreement. Where several successive modifications are made, this limit applies to the value of each modification. Such successive modifications may not be used to circumvent the legislation on public procurement.
The condition stated in the first paragraph, 3°, does not apply to contracts awarded by contracting entities pursuing activities in the water, energy, transport and postal services sectors as referred to in Title 3 of the Act.
For the calculation of the amount referred to in the first paragraph, 3°, where the contract contains an indexation clause, the updated value is used as the reference value.