§ 1 The contractor is deemed to be in default in the performance of the contract:
   1° where the services are not performed in accordance with the requirements laid down in the procurement documents;
   2° regardless of the time, where the services are not progressing in such a way that they can be fully completed by the dates set;
   3° where he fails to comply with the written orders validly given by the contracting body.
§ 2 All breaches of the provisions of the contract, including failure to comply with the orders of the contracting body, shall be recorded in a report, a copy of which shall be sent immediately to the contractor by registered mail or by electronic means which similarly guarantees the exact date of dispatch.
The contractor shall remedy his breaches without delay. He may put forward his defence to the contracting body by registered mail or by electronic means which similarly guarantees the exact date of dispatch. He must send this defence within fifteen days following the date of dispatch of the report. His silence after that period is deemed to be an admission of the facts established.
If the contracting body has been informed, in accordance with Article 49/1 of the Social Criminal Code, that the contractor or a subcontractor in the subcontracting chain, at whatever place and for whatever share the latter is involved, has seriously failed in its obligation to pay its employees in time the wages to which they are entitled, the fifteen-day defence period referred to in the second paragraph shall be reduced to a period to be determined by the contracting body. The same applies where the contracting body finds, or is aware, that the contractor or a subcontractor in the subcontracting chain, at whatever place and for whatever share the latter is involved, employs one or more illegally staying third-country nationals. The shortened period may not, however, be shorter than five working days in the case of a serious failure as regards the payment of wages, and two working days in the case of the employment of illegally staying third-country nationals.
§ 3 Where breaches are found on the part of the contractor, he is exposed to sanctions through the application of one or more of the measures laid down in Articles 45 to 49, 85 to 88, 123, 124, 154 and 155.