# Performance Decree, Article 49

- URL: https://procurelex.be/en/performance-decree/49 · Nederlands: https://procurelex.be/nl/kb-uitvoering/49
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2017-06-22/01, art. 27 (in force 30-06-2017)

Where the contractor, after the expiry of the period laid down in Article 44, § 2, for putting forward his defence, has put forward no arguments or has put forward arguments which the contracting body considers unjustified, the latter shall take one or more of the following measures, if at any time it finds that the contractor has failed to comply with the provisions of Article 5, second paragraph, of the Act or of Article 10 of the Defence and Security Act, as the case may be:
   1° the application of an ex officio measure. In the event of unilateral termination of the contract by the contracting body, this does not entail that the latter acquires the entire surety as liquidated damages or, in the absence of a surety, an equivalent amount;
   2° in the case of a works contractor, a proposal for a sanction pursuant to Article 19 of the Act of 21 March 1991 regulating the accreditation of works contractors;
   3° the exclusion decision referred to in Article 48.
Where the contracting body takes a measure under this Article, it shall inform the auditor-general of the Belgian Competition Authority thereof without delay. The notification shall contain a description of the contract concerned, a copy of the main documents and a reference to this Article.