# Performance Decree, Article 64. Acceptances and guarantees

- URL: https://procurelex.be/en/performance-decree/64 · Nederlands: https://procurelex.be/nl/kb-uitvoering/64
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel

The services are accepted only after the checks, inspections and prescribed tests have proved satisfactory. As the case may be, provision is made for provisional acceptance after completion of the services forming the subject of the contract and, upon expiry of the guarantee period, for final acceptance marking the complete termination of the contract, except where Articles 1792 and 2270 of the Civil Code apply to the contracts to which they relate.
As regards a framework agreement concluded with a single contractor, unless otherwise provided in the procurement documents, the last acceptance for a contract concluded on the basis of the framework agreement counts as acceptance of the framework agreement.