# Performance Decree, Article 68. Payment in the event of opposition to payment or garnishment by a third party

- URL: https://procurelex.be/en/performance-decree/68 · Nederlands: https://procurelex.be/nl/kb-uitvoering/68
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2014-05-22/03, art. 6 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21); KB 2017-06-22/01, art. 2 (in force 30-06-2017); KB 2024-08-12/15, art. 5 (in force 01-01-2025)

In the event of opposition to payment or of a protective garnishment by a third party against the contractor, the processing period is suspended .... The suspension ends on the day on which the contracting body is informed that the obstacle to payment has been lifted.