# Performance Decree, Article 73

- URL: https://procurelex.be/en/performance-decree/73 · Nederlands: https://procurelex.be/nl/kb-uitvoering/73
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2017-06-22/01, art. 2 (in force 30-06-2017); KB 2017-06-22/01, art. 36 (in force 30-06-2017)

§ 1 Any legal action by the contractor based on the facts or circumstances referred to in Articles 38/9, 38/11 and 38/12 must, on pain of forfeiture of the right of action, be made known in writing beforehand within the periods laid down in Articles 50, 38/15 or 38/16 and be the subject of a written request.
§ 2 Any summons before the court at the request of the contractor and relating to a contract shall, on pain of forfeiture of the right of action and without prejudice to paragraph 1, be served on the contracting body no later than thirty months following the date of service of the report of provisional acceptance. Where, however, the summons originates in facts or circumstances that arose during the guarantee period, it must be served, on pain of forfeiture of the right of action, no later than thirty months after the expiry of the guarantee period. If the drawing up of a report is not required, the period starts from final acceptance.
§ 3 Where the dispute has been the subject of discussions between the parties and the decision of the contracting body was served less than three months before the expiry of these periods or not at all within these periods, they are extended until the end of the third month following that of the service of the decision.