# Performance Decree, Article 76. Performance periods

- URL: https://procurelex.be/en/performance-decree/76 · Nederlands: https://procurelex.be/nl/kb-uitvoering/76
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21); KB 2017-06-22/01, art. 2 (in force 30-06-2017); KB 2017-06-22/01, art. 37 (in force 30-06-2017)

§ 1 The performance period may relate to the entire contract. The contract may also consist of several parts or phases, each with its own performance period and its own amount. If the contract does not consist of parts or phases, the procurement documents may moreover lay down partial performance periods, which may or may not be binding.
§ 2 The contracting body determines the starting date of the works. Except for contracts awarded during the winter period and whose performance must be postponed until the favourable season, the starting date of the works must fall:
   1° for ordinary works whose contract sum corresponds to or is lower than class 5 of the regulations governing the accreditation of works contractors: between the fifteenth and the sixtieth day following the day of conclusion of the contract;
   2° for works whose contract sum corresponds to or is higher than class 6 of the same regulations: between the thirtieth and the seventy-fifth day following the day of conclusion of the contract;
   3° for works whose contract sum corresponds to or is lower than class 5 of the same regulations but for which special techniques or materials must be used, the arrangements of 2° apply. The procurement documents state whether that case applies to the contract.
At least fifteen days must elapse between the dispatch of the letter fixing the start of the works and the date set for that purpose. This provision does not, however, apply:
   1° in case of urgency;
   2° unless otherwise provided in the procurement documents, to any phase or part other than the first of one and the same contract;
   3° to contracts following a first contract concluded with the same contractor on the basis of a framework agreement.
The contractor is obliged to start the works on the day notified to him and to continue them regularly so that they are fully completed within the contractually agreed performance period.
§ 3 The contractor has the right to demand termination of the contract where the contracting body has not fixed the starting date of the works after the expiry of the one hundred and twentieth or one hundred and fiftieth day after the conclusion of the contract, depending on whether the respective periods of sixty or seventy-five days referred to above apply to the contract. The contractor may request termination of the contract by registered mail or by electronic means which similarly guarantees the exact date of dispatch within a period of at most thirty days after service of the order to start the works.
§ 4 Where the performance period is set in working days, the following are not counted as such:
   1° Saturdays, except those on which the contractor has or should have worked because of the distribution of working time on the construction site;
   2° Sundays and public holidays;
   3° paid annual leave days and compensatory rest days laid down by royal decree or in a collective labour agreement made generally binding by royal decree;
   4° days on which, as accepted by the contracting body, work was or would have been impossible for at least four hours because of adverse weather conditions or their consequences.
Where, however, for economic reasons, the performance period of the contract is expressed not in working days but in days, weeks, months or years, or from one date to another or by a given end date, all days are counted without distinction in this period. If the original performance period in that case does not exceed eighty days, the compulsory holiday period is deemed not to be included in this performance period, insofar as this holiday period falls within the performance period.
§ 5 If the contractor has to work outside the limits set by law, he shall let the contracting body assess the reality of this situation and shall request the necessary permissions from the competent authorities for that purpose.