# Performance Decree, Article 79. Organisation of the construction site

- URL: https://procurelex.be/en/performance-decree/79 · Nederlands: https://procurelex.be/nl/kb-uitvoering/79
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2017-06-22/01, art. 2 (in force 30-06-2017)

Without prejudice to the legislation on the well-being of employees in the performance of their work, the contractor is responsible for order on the construction site for the duration of the works, and is obliged, in the interest of the officials of the contracting body and of third parties as well as of his own staff, to take all necessary measures to guarantee their safety.
The contractor shall, on his full responsibility and at his expense, take all the measures that are indispensable for the protection, preservation and integrity of the existing structures and works. He shall also take all precautions required by the art of building and by the particular circumstances in order to safeguard neighbouring properties and to avoid disturbances being caused to them through his fault.