# Performance Decree, Article 81. Fluctuation of the estimated quantities

- URL: https://procurelex.be/en/performance-decree/81 · Nederlands: https://procurelex.be/nl/kb-uitvoering/81
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21); KB 2017-06-22/01, art. 2 (in force 30-06-2017)

Where, independently of any modification to the contract made by the contracting body, the quantities actually performed of an item according to the price list exceed three times, or fall below half of, the estimated quantities, either party may request revision of the original unit prices and performance periods.
Even where the thresholds mentioned in the previous paragraph have not been reached, the performance period may be adjusted to the quantities actually performed where their size so justifies.
In the event of an excess, the revised prices, if any, apply only to the quantities performed that exceed three times the estimated quantities.
The party requesting the revision must inform the other party of its intention to revise the unit prices and/or periods no later than thirty days after the drawing up of the progress statement establishing that the quantity performed has reached three times, or less than half of, the estimated quantity. This notification shall be made by registered mail or by electronic means which similarly guarantees the exact date of dispatch.
After the expiry of this period, this notification applies only to the quantities performed from the date of this notification.
In any event, the claiming party shall justify the new unit prices and/or periods resulting from that new situation.
In the absence of agreement on the new unit prices, the contracting body shall fix ex officio the prices that it considers justified, without prejudice to all rights of the contractor.
The contractor is obliged to continue the works without interruption, regardless of the disputes to which the fixing of the new unit prices might give rise.