# Performance Decree, Article 83. Works journal

- URL: https://procurelex.be/en/performance-decree/83 · Nederlands: https://procurelex.be/nl/kb-uitvoering/83
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21); KB 2017-06-22/01, art. 2 (in force 30-06-2017)

§ 1 A works journal, drawn up in the form accepted by the contracting body and supplied by the contractor, is kept on each construction site by the contracting body and exclusively by it. It shall record therein daily, inter alia, the following information:
   1° the weather conditions, work stoppages due to adverse weather conditions, working hours, the number and capacity of the workers employed on the construction site, the materials delivered, the equipment used, equipment out of service, the tests carried out on site, the samples sent, unforeseen circumstances, as well as purely incidental and less important orders to the contractor;
   2° detailed notes of all the elements verifiable on the construction site that are useful for calculating the payments to be made to the contractor, such as works performed, quantities performed, products delivered that may be charged. These detailed notes form an integral part of the works journal, but may, where applicable, be recorded in annexes to the journal;
   3° where applicable, the data and remarks corresponding to the content of the coordination journal referred to in the regulations on temporary or mobile construction sites.
§ 2 Without prejudice to any obligations regarding the keeping of the coordination journal, the contracting body is free not to keep a works journal or part of it. In that case, it shall state this in the procurement documents.
However, the detailed notes must always be kept in the case of contracts at prices other than global prices.
§ 3 The information stated in the works journal and in the detailed notes comes from the contracting body, the contractor and, where applicable, the safety and health coordinator. At the request of the contracting authority, the contractor shall provide all useful information for the proper keeping of the works journal.
The entries in the works journal and in the detailed notes shall be signed by the contracting body and countersigned by the contractor or his representative, and, where applicable, by the safety and health coordinator.
§ 4 If there is disagreement on this, the contractor shall make his remarks known to the contracting body by registered mail or by electronic means which similarly guarantees the exact date of dispatch, sent within fifteen days after the disputed entry or detailed notes. He shall formulate his remarks clearly and in detail.
If he does not communicate his remarks in the manner and within the period described above, the contractor is deemed to agree with the entries in the works journal and in the detailed notes.
Where these remarks are not considered well founded, the contractor shall be informed thereof by registered mail or by electronic means which similarly guarantees the exact date of dispatch.