# Performance Decree, Article 84. Liability of the contractor

- URL: https://procurelex.be/en/performance-decree/84 · Nederlands: https://procurelex.be/nl/kb-uitvoering/84
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel

§ 1 The contractor is liable for all works carried out by him or by his subcontractors until final acceptance of all the works.
During the guarantee period, the contractor must, as required, carry out on the construction all the works and repairs necessary to keep it in good condition or in good working order.
After provisional acceptance, the contractor is, however, not liable for damage for which he is not at fault.
§ 2 From provisional acceptance and without prejudice to the provisions of paragraph 1 concerning his obligations during the guarantee period, the contractor is liable for the solidity of the construction and for the proper performance of the works, in accordance with Articles 1792 and 2270 of the Civil Code.