# Performance Decree, Article 87. Ex officio measures

- URL: https://procurelex.be/en/performance-decree/87 · Nederlands: https://procurelex.be/nl/kb-uitvoering/87
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21); KB 2017-06-22/01, art. 2 (in force 30-06-2017); KB 2017-06-22/01, art. 41 (in force 30-06-2017)

§ 1 Where it is found that the contractor has defaulted before the order to start the works has been issued, the absence of this order does not preclude the application of ex officio measures.
Where the works have already been started, the defaulting contractor shall stop his works from the day indicated to him. All works carried out thereafter remain acquired free of charge by the contracting authority.
After the contractor has been summoned for that purpose, a statement is drawn up of the state of the works, the equipment and the materials delivered to the construction site.
The contracting body may proceed to any construction or demolition or to the taking of any other measure that it considers necessary for the preservation and proper performance of the works.
Except in the event of termination of the contract, the contracting body is entitled, against payment, to use the equipment and materials of the contractor, of which it provides him with the list, in order to continue the contract or to have it continued.
The contractor is obliged to remove from the construction site, within the shortest possible time, his equipment and materials which the contracting body does not wish to retain.
The contractor may follow the works carried out at his expense, without however hindering the execution of the orders of the contracting body.
Notices concerning the place and date of acceptance of the construction carried out at his expense shall be served on the defaulting contractor, either by registered mail or by electronic means which similarly guarantees the exact date of dispatch, or by means of a written document of which the contractor acknowledges receipt.
§ 2 Where the measures referred to in Article 47, § 2, first paragraph, 2° and 3°, are applied, the penalties for delay are imposed at their maximum amount, in accordance with Article 86, § 6.
In addition to the amount of the penalties, the penalties for late performance and the demolition costs, the extra costs resulting from the new method of performance are borne by the defaulting contractor.
The aforementioned extra costs constitute the positive difference between, on the one hand, the amount of the works carried out ex officio, increased where appropriate by value added tax, and, on the other hand, the amount, increased where appropriate by value added tax, that would have been charged for those works by the defaulting contractor. If that difference is negative, it remains acquired by the contracting body.
The following are not taken into account in calculating the extra costs for the works carried out at the expense of the defaulting contractor:
   1° within the limits of Article 80, § 1, the additional or omitted works ordered ex officio by the contracting body after notification of the decision to take ex officio measures;
   2° the price revisions referred to in Article 38/7, § 1;
   3° the new unit prices agreed with the contractor charged with the performance of the contract at the defaulting contractor's expense, in application of Articles 80, § 2, and 81.
The costs of entering into the new contract or contracts at the defaulting contractor's expense are likewise borne by the defaulting contractor. Regardless of the award method used for the contract or contracts, these costs are charged at one per cent of the original contract sum of that contract or those contracts, without exceeding fifteen thousand euro.
§ 3 Where the contractor fails during the guarantee period to fulfil his obligations in accordance with Article 84, § 1, the contracting body may, after notice of default by report in accordance with Article 44, § 2, carry out or have carried out the repair and reconstruction works at the expense of the contractor in default.
The same applies where the contractor fails, upon expiry of the guarantee period, to fulfil his obligations in accordance with Article 84, § 2.