# Performance Decree, Article 95. Payments

- URL: https://procurelex.be/en/performance-decree/95 · Nederlands: https://procurelex.be/nl/kb-uitvoering/95
- Royal Decree of 14 January 2013 establishing the general rules for the performance of public contracts, consolidated version in force from 2025-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/besluit/2013/01/14/2013021005/justel
- Amended by: KB 2024-08-12/15, art. 8 (in force 01-01-2025)

§ 1 Both for interim payments and for payment of the balance or the one-off payment of the contract sum, the contractor submits a dated and signed claim for payment based on a detailed statement of the works carried out, which in its view justify the payments requested.
This detailed statement may include:
   1° the quantities carried out on the basis of the items of the summary bill of quantities;
   2° the quantities carried out in excess of the estimated quantities of the items of the summary bill of quantities;
   3° additional works carried out on written order;
   4° the works carried out at unit prices proposed by the contractor and not yet accepted by the contracting body.
§ 2 After receipt of each claim for payment, the contracting body carries out the following operations within the processing period referred to in § 3, first paragraph:
   1° verification of the statement of works submitted and the making of any corrections to that document. Where it contains prices that have not been agreed between the parties, the contracting body sets those prices of its own motion, without prejudice to all rights of the contractor;
   2° drawing up a report stating the works accepted for payment and the amount which, in the contracting body's view, is owed. The contracting body notifies the contractor of this report in writing and requests it to submit an invoice for the amount stated within five days.
§ 3 The contracting body carries out the verification and the payment of the amount owed to the contractor within a processing period of thirty days from the date on which it received the claim for payment and the detailed statement of the works carried out referred to in § 1. Payment may, however, take place only insofar as the contracting body has the duly drawn-up invoice, as well as the other documents, if any, that are required.
The processing period referred to in the first paragraph is sixty days for contracts awarded by contracting bodies that provide health care and that are specifically recognised for that purpose, but only for the works connected with that specific activity.
An exception is made to the first paragraph in the following cases:
- if the date of receipt of the claim for payment is not established, the verification and the payment take place within a period of thirty days after the date of receipt of the detailed statement of the works carried out;
- if the contracting body receives the claim for payment before the works established by the detailed statement of the works carried out have been completed, the verification and the payment take place within a period of thirty days after the completion of the works.
§ 4 The processing period is suspended in proportion to the number of days:
   1° by which the period of five days granted to the contractor by § 2, 2°, for submitting its invoice is exceeded;
   2° needed to receive the contractor's reply, where the contracting body, in the context of joint and several liability, has to question it about the actual amount of its social or tax debt as referred to in Article 30bis, § 4, and 30ter, § 4, of the Act of 27 June 1969 revising the Decree-Law of 28 December 1944 on the social security of workers, and in Article 55 of the Code for the amicable and compulsory recovery of tax and non-tax claims.