# Remedies Act, Article 17

- URL: https://procurelex.be/en/remedies/17 · Nederlands: https://procurelex.be/nl/rechtsbescherming/17
- Act of 17 June 2013 on reasoning, information and remedies in respect of public contracts, certain works, supply and service contracts and concessions, consolidated version in force from 2026-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/wet/2013/06/17/2013203640/justel
- Amended by: W 2017-02-16/19, art. 4 (in force 30-06-2017); W 2017-02-16/19, art. 26 (in force 30-06-2017)

At the request of any interested party, the review body declares the contract or concession concluded ineffective in each of the following cases:
   1° without prejudice to Article 18, where the contracting body has concluded a contract or concession without publication at European level of a contract notice or concession notice, although European Union law on public contracts or concessions or the legislation on public contracts or concessions nevertheless requires this;
   2° where the contracting body has concluded the contract or the concession without observing the period referred to in Article 11, first paragraph, or without waiting until the review body, where applicable of first instance, has ruled, either on the action for suspension or on the action for interim measures, where:
      a) a tenderer has, as a result of this infringement, been unable to bring or complete the remedy for suspension as referred to in Article 11, second paragraph, and
      b) this infringement is combined with an infringement of European Union law on public contracts or concessions or of the legislation on public contracts or concessions, as a result of which the chances of a tenderer of obtaining the contract or the concession were adversely affected,
   3° where the contracting body has concluded a contract on the basis of a framework agreement without all the conditions already being laid down in that framework agreement, where the procedural rules laid down in that respect by the King are not complied with.
The contracting body and the contractor or concessionaire are made parties to this review procedure. To that end, the contracting body communicates the identity of the contractor or concessionaire as soon as the person bringing the remedy so requests.
The action for a declaration of ineffectiveness of a contract or a concession may be filed together with the action for annulment referred to in Article 14 or separately.