# Remedies Act, Article 38

- URL: https://procurelex.be/en/remedies/38 · Nederlands: https://procurelex.be/nl/rechtsbescherming/38
- Act of 17 June 2013 on reasoning, information and remedies in respect of public contracts, certain works, supply and service contracts and concessions, consolidated version in force from 2026-01-01; consolidated Dutch text (prevails): https://www.ejustice.just.fgov.be/eli/wet/2013/06/17/2013203640/justel
- Amended by: W 2017-02-16/19, art. 4 (in force 30-06-2017)

The decision referred to in Article 37 serves as a record and shall be forwarded, at its request, to the European Commission. Where applicable, this record shall be supplemented with:
   1° an indication of the part of the contract or of the framework agreement that the beneficiary intends or is obliged to subcontract;
   2° the justification, in the event of a negotiated procedure without publication, for exceeding the duration of five years for contracts relating to additional supplies as referred to in Article 25, 3°, a), second paragraph, of the Defence and Security Act or for contracts consisting of the repetition of similar works or services as referred to in Article 25, 4°, b), second paragraph, of the same Act;
   3° the justification, in the event of a negotiated procedure without publication, for exceeding the ceiling of 50 % of the amount of the main contract for the additional works or services as referred to in Article 25, 4°, a), second paragraph, of the Defence and Security Act;
   4° an indication of the reasons why the duration of the framework agreement is longer than seven years.