Act of 17 June 2016 · Title 1 · Introductory provision, definitions and general principles
Article 12/6. Public Procurement Act
Chapter 2. – General principles
Where an advance payment is granted and the public contract concerned is part of a project for which a permit is required, the contracting body may make the granting of the advance payment dependent on obtaining that permit, by means of a provision to that effect in the procurement documents.
For the purposes of Articles 12/1 to 12/5, a framework agreement is not regarded as a public contract, but a contract based on a framework agreement is regarded as a public contract.
Amended byIngevoegd bij W 2023-12-22/14, art. 3 (in force 01-01-2024)
Previous article
12/5 — Where the duration of the contract is twelve months or less, the reference…
Next article
12/7 — Contracting bodies shall complete the fields relating to advance payments of…