Time limits in Belgian public procurement

The time limits of the Public Procurement Act for tenders and requests to participate, and the standstill period, each with the provision it is read from, and a calculator that counts one of them from a date.

Updated 22 November 2026Draft – awaiting legal review

Count a time limit

Choose a time limit and the date of the fact it runs from. The count shows the first day, the last day counted and where the period ends.

A draft aid, not legal advice: the counting rule has not been reviewed by a lawyer. Check the date against the provision and the facts of your procedure.

How the days are counted here

  • The day of the fact (the publication, the dispatch, the notice) does not count: the period starts on the next day.
  • Saturdays, Sundays and public holidays count, unless the provision speaks of working days.
  • A period that ends on a Saturday, a Sunday or a public holiday ends on the next working day.

This is the rule of Regulation (EEC, Euratom) No 1182/71, by which the periods of the procurement directives are counted. Whether Belgian law counts its own periods, such as the standstill period, the same way has not yet been reviewed by a lawyer.

Tenders and requests to participate

Time limitWhatCounted fromLegal basis
35 daysminimumOpen procedure: receipt of tendersdispatch of the contract noticeArticle 36, § 1, second paragraph
5 daysreductionOpen procedure: reduction when tenders are submitted electronically—Article 36, § 4
30 daysminimumRestricted procedure: receipt of requests to participatedispatch of the contract noticeArticle 37, § 1, second paragraph
30 daysminimumRestricted procedure: receipt of tendersdispatch of the invitation to tenderArticle 37, § 2, second paragraph
30 daysminimumInnovation partnership: receipt of requests to participatedispatch of the contract noticeArticle 40, § 1, fourth paragraph
30 daysminimumCompetitive dialogue: receipt of requests to participatedispatch of the contract noticeArticle 39, § 1, third paragraph
30 daysminimumCompetitive procedure with negotiation: receipt of requests to participatedispatch of the contract noticeArticle 38, § 3, third paragraph

Review

Time limitWhatCounted fromLegal basis
15 daysminimumStandstill perioddispatch of the notification of the award decisionArticle 11, Remedies Act

Public holidays in 2026

The public holidays fixed by law, which the count treats as non-working days.

  • 1 January 2026New Year's Day
  • 6 April 2026Easter Monday
  • 1 May 2026Labour Day
  • 14 May 2026Ascension Day
  • 25 May 2026Whit Monday
  • 21 July 2026National Day
  • 15 August 2026Assumption Day
  • 1 November 2026All Saints' Day
  • 11 November 2026Armistice Day
  • 25 December 2026Christmas Day

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.