Royal Decree of 18 April 2017 · Title 1 · General provisions
Article 34. Award Decree
Chapter 5. – Correction of errors and verification of prices or costs
§ 1 The contracting authority corrects the tenders in light of the arithmetical errors and purely clerical errors in the procurement documents identified by it or by a tenderer.
§ 2 The contracting authority corrects the arithmetical errors and purely clerical errors in the tenders, without being liable for errors that are not discovered.
In order to correct the arithmetical errors and purely clerical errors in the tenders that it identifies, the contracting authority ascertains the tenderer's real intention by means of an overall analysis of the tender and by comparing it with the other tenders and with market prices. If, after analysis of the tender, this intention is not sufficiently clear, the contracting authority may, within a time limit set by it, invite the tenderer to clarify the content of its tender without changing or supplementing it, and this without prejudice to the possibility of negotiating if the procedure so permits.
If, in this latter case, no explanation has been given or the explanation is not acceptable to the contracting authority, it corrects the errors according to its own findings. Should this not be possible, the contracting authority may either decide that the unit prices stated apply, or reject the tender as irregular.
§ 3 If the contracting authority corrects errors in the tenders directly, it keeps the original version of those tenders and ensures that its corrections are clearly identifiable, while the original data also remain visible.
Previous article
33 — After the correction of the tenders in accordance with Article 34, the…
Next article
35 — The contracting authority subjects the tenders submitted to a price or cost…
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.