Act of 17 June 2016 · Title 3 · General provisions
Article 28. Price
§ 1 Where the concession provides for a price, it is a lump sum, save for an exception duly reasoned in the concession documents.
§ 2 The lump-sum basis does not preclude the revision of the price in the light of certain economic or social factors, provided that the concession contract contains a clear, precise and unambiguous price revision clause.
The price revision clause must take account of the price trend of the main components of the costs and investments. The King shall lay down the detailed rules for this price revision.
Where the concessionaire has recourse to subcontractors, the revision must, where applicable, also be applied to their prices, in accordance with the detailed rules to be laid down by the King and to the extent corresponding to the nature of the services performed by them.
Article 57 of the Act of 30 March 1976 on economic recovery measures does not apply to concession contracts, nor to the contracts concluded by the concessionaire with the subcontractors and the contracts concluded between subcontractors.
§ 3 The lump-sum basis of the price paid by the contracting body likewise does not preclude a revision of the concession in the event of a disruption of its contractual balance, without prejudice to the application of Article 57. The King shall lay down the conditions and the procedure for the application of the revision mechanism.
Cross-references