Article 147. Performance periods
§ 1 The performance period is set either in working days or in days, weeks or months, or else from date to date.
Where the performance period is set in working days, the following are not regarded as such:
1° Saturdays, Sundays and public holidays;
2° paid annual leave days and compensatory rest days determined in a Royal Decree or in a collective labour agreement made generally binding by Royal Decree.
Where the performance period is set in days, weeks or months, the closing days for annual holidays in the service provider's undertaking are not counted, unless the performance period constituted an award criterion of the contract.
§ 2 The performance period begins, as the case may be, either on the day following the date on which the contract was concluded, or on the day of the order.
The performance period includes the time needed for the preparation of the services, in particular any preliminary technical inspections.
Previous article
146 — Arrangements for performance
Next article
148 — Services with fixed quantities or minimum services to be provided
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.