Royal Decree of 14 January 2013 · Title 6 · Specific provisions for public service contracts

Article 147. Performance periods

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 The performance period is set either in working days or in days, weeks or months, or else from date to date.

Where the performance period is set in working days, the following are not regarded as such:

1° Saturdays, Sundays and public holidays;

2° paid annual leave days and compensatory rest days determined in a Royal Decree or in a collective labour agreement made generally binding by Royal Decree.

Where the performance period is set in days, weeks or months, the closing days for annual holidays in the service provider's undertaking are not counted, unless the performance period constituted an award criterion of the contract.

§ 2 The performance period begins, as the case may be, either on the day following the date on which the contract was concluded, or on the day of the order.

The performance period includes the time needed for the preparation of the services, in particular any preliminary technical inspections.