Royal Decree of 14 January 2013 · Title 6 · Specific provisions for public service contracts

Article 159. Contract price in the event of delay in performance

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

The price of the services performed during a period of delay attributable to the service provider is determined as follows, on the basis of the calculation method that is most favourable to the contracting body:

1° either by assigning to the constituent factors of the prices that are designated in the contract for revision the values that applied during the period of delay concerned;

2° or by assigning to each of those factors an average value (E) determined by the following formula:

(Formula not reproduced for technical reasons, see Belgian Official Gazette of 14-02-2013, p. 8857)

where:

e1, e2,... en, the successive values of the factor concerned during the contractual period, extended where applicable to the extent that the delay was not attributable to the contractor;

t1, t2,.. tn, the corresponding duration of each value, expressed in months of thirty days. A part of a month and the duration of suspensions in the performance of the contract are not taken into account.

The value of E is calculated to the second decimal place.

Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)