Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 24. Insurance
Section 3. – Financial guarantees
§ 1 The contractor shall take out the insurance covering its liability for industrial accidents, as well as its civil liability towards third parties in the performance of the contract.
The contractor shall also take out all other insurance imposed by the procurement documents.
§ 2 Within a period of thirty days after the conclusion of the contract, the contractor shall demonstrate that it has entered into these insurance contracts, by means of a certificate showing the extent of the insured liability required by the procurement documents.
At any time during the performance of the contract, the contractor shall produce this certificate within a period of fifteen days after receipt of the request of the contracting body.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)