Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts
Article 77. Making land and premises available
Section 1. – Provisions applicable to all works contracts
The land occupied by the works or the construction is made available to the contractor free of charge by the contracting body. Outside that land, the contractor shall himself ensure that he obtains the use of the land which he considers necessary for the performance of the contract. Where the contracting body wishes to provide the contractor with this land in whole or in part, this is indicated in the procurement documents.
Where premises are made available to the contractor for any use whatsoever, he must keep those premises in good condition for as long as he uses them and, if requested, must restore them to their original condition at the end of the contract.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.