Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts

Article 82. Means of control

Section 1. – Provisions applicable to all works contracts

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 The contractor shall notify the contracting body of the exact place of performance of the works on the construction site, in his workshops, or with his subcontractors or his suppliers.

The tests and checks for the inspection of the products shall be carried out, at the choice of the contracting body, either:

1° on the construction site or at the place of delivery;

2° in the workshops of the producer;

3° in the laboratories of the contracting body or those accepted by it;

4° in the laboratories referred to in the legislation on the accreditation of conformity assessment bodies.

Without prejudice to the inspections that must be carried out on the construction site, the contractor shall ensure that the supervising official and the representatives appointed by the contracting body have free access at all times to the place of production, in order to check strict compliance with the contract, inter alia as regards the origin and quality of the products.

Where the contracting body supervises the place of production, no delivery may, on pain of rejection, be dispatched to the construction site before it has been approved for dispatch by the representative of the contracting body.

Where the products are manufactured under permanent control in a particular workshop, they may be dispatched without further verification by the contracting body.

§ 2 Where the results of the tests are disputed, each of the parties has the right to request a counter-test.

The counter-test consists of examining the properties that gave a negative result in the first test. All the results of the counter-test must be satisfactory.

The results of the counter-tests are decisive.

The costs of the counter-test are borne by the losing party.

A corresponding extension of the performance period is granted to the extent that the counter-test finds in favour of the contractor, and provided that he proves that the performance of his works was thereby delayed. This extension excludes any right to damages.

§ 3 Accepted products that are on the construction site remain there under the supervision of the contractor. They may no longer be removed from the construction site without the permission of the contracting body.

The contracting body becomes the owner of the products delivered to the construction site for incorporation as soon as they have been accepted for payment. The contractor nevertheless remains responsible for these products until provisional acceptance of the contract.

§ 4 Rejected products shall be removed by the contractor and taken away from the construction site within fifteen days after service of the report of rejection. Failing this, they shall be removed ex officio by the contracting body at the expense and risk of the contractor.

Any use of rejected products results in the ex officio refusal of acceptance of the contract.

Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2017-06-22/01, art. 40 (in force 30-06-2017)