Skip to content

Act of 17 June 2013 · Title II · Reasoning, information and remedies for public contracts falling under the Public Procurement Act and for concessions falling under the Concessions Act

Article 13. Remedies Act

Chapter 1. – Contracts and concessions reaching the European thresholds — Section 4. – Standstill period

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

The suspension of the implementation of the award decision by the review body leads by operation of law to the suspension of the performance of the contract or the concession which would have been concluded in breach of Article 11.

The contracting body notifies the contractor or concessionaire of this suspension without delay and orders him not to begin or to stop the performance of the contract or of the concession, as the case may be.

Where, following the suspension by operation of law of the performance of the contract or the concession, no action for annulment of the award decision or for declaration of ineffectiveness of the contract or the concession is filed within the applicable time limits laid down in Article 23, both the suspension of the implementation of the award decision and that of the contract or the concession are lifted by the review body.

Amended byW 2017-02-16/19, art. 22 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.