Act of 17 June 2013 · Title II · Reasoning, information and remedies for public contracts falling under the Public Procurement Act and for concessions falling under the Concessions Act

Article 17. Remedies Act

Chapter 1. – Contracts and concessions reaching the European thresholds — Section 5. – Review procedures — Subsection 4. – Declaration of ineffectiveness

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

At the request of any interested party, the review body declares the contract or concession concluded ineffective in each of the following cases:

1° without prejudice to Article 18, where the contracting body has concluded a contract or concession without publication at European level of a contract notice or concession notice, although European Union law on public contracts or concessions or the legislation on public contracts or concessions nevertheless requires this;

2° where the contracting body has concluded the contract or the concession without observing the period referred to in Article 11, first paragraph, or without waiting until the review body, where applicable of first instance, has ruled, either on the action for suspension or on the action for interim measures, where:

a) a tenderer has, as a result of this infringement, been unable to bring or complete the remedy for suspension as referred to in Article 11, second paragraph, and

b) this infringement is combined with an infringement of European Union law on public contracts or concessions or of the legislation on public contracts or concessions, as a result of which the chances of a tenderer of obtaining the contract or the concession were adversely affected,

3° where the contracting body has concluded a contract on the basis of a framework agreement without all the conditions already being laid down in that framework agreement, where the procedural rules laid down in that respect by the King are not complied with.

The contracting body and the contractor or concessionaire are made parties to this review procedure. To that end, the contracting body communicates the identity of the contractor or concessionaire as soon as the person bringing the remedy so requests.

The action for a declaration of ineffectiveness of a contract or a concession may be filed together with the action for annulment referred to in Article 14 or separately.

Amended byW 2017-02-16/19, art. 4 (in force 30-06-2017) · W 2017-02-16/19, art. 26 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.