Skip to content

Act of 17 June 2013 · Title II · Reasoning, information and remedies for public contracts falling under the Public Procurement Act and for concessions falling under the Concessions Act

Article 5/1. Remedies Act

Chapter 1. – Contracts and concessions reaching the European thresholds — Section 2. – Reasoned decision

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

The reasoned decision referred to in Article 4/1 contains, depending on the award procedure and the type of decision:

1° the name and address of the contracting body, the date of the decision, the subject matter of the concession and, where applicable, the price or the amount of the payments to be approved;

2° in the case of the award procedures referred to in Article 43, § 2, of the Concessions Act, the legal and factual reasons justifying or allowing the use of this procedure;

3° the names of the candidates or tenderers;

4° the names of the candidates or tenderers selected or not selected and the legal and factual reasons justifying their selection or non-selection;

5° the names of the tenderers whose tender has been found non-compliant and the legal and factual reasons for their rejection. These reasons relate in particular to compliance with the minimum technical, material, functional or legal requirements which the contracting body has, where applicable, laid down in the concession documents;

6° the names of the tenderer chosen or of one or more participants chosen and of the participants and tenderers whose compliant tender was not chosen and the legal and factual reasons, including the characteristics and relative advantages of the tender chosen, for the decisions relating to them;

7° the legal and factual reasons for the decision of the contracting body to refrain from awarding the concession and, where applicable, the indication of the new award procedure to be followed.

Amended byIngevoegd bij W 2017-02-16/19, art. 12 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by