Royal Decree of 18 April 2017 · Title 2 · Award by open or restricted procedure
Article 81. Award Decree
Chapter 3. – Interpretation, errors and omissions
If an economic operator discovers in the procurement documents errors or omissions of such a nature that they make the calculation of the price or the comparison of the tenders impossible, it shall report this immediately and in writing to the contracting authority. In any event, it shall notify the latter at the latest ten days before the final date for the receipt of tenders, unless this is impossible because of the shortening of the time limit for the receipt of tenders.
The contracting authority shall judge whether the errors or omissions are sufficiently important to proceed to a corrigendum or to another form of adapted publication and, if necessary and having regard to Article 9, second and third paragraphs, to extend the time limit for the submission of tenders.
Cross-references
This article refers to
Previous article
80 — Unless otherwise provided in the procurement documents, the following order of…
Next article
82 — After the final date and time for the submission of tenders, as possibly…
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.