Royal Decree of 18 April 2017 · Title 2 · Award by open or restricted procedure
Article 82. Award Decree
Chapter 3. – Interpretation, errors and omissions
After the final date and time for the submission of tenders, as possibly extended, the tenderer no longer has the right to rely on errors or omissions occurring in the summary bill of quantities or the inventory as provided by the contracting authority.
Moreover, from that moment it can no longer rely on formal defects, errors or omissions in its tender.
Amended byKB 2018-04-15/01, art. 39 (in force 28-04-2018)