Royal Decree of 18 April 2017 · Title 2 · Award by open or restricted procedure
Article 89. Award Decree
Chapter 7. – Conclusion of the contract
If the commitment period, as possibly extended, expires without the contract having been concluded and the contracting authority does not at this stage apply Article 85 of the Act, it shall proceed as follows.
Before awarding the contract, the contracting authority shall ask the tenderer in question in writing whether it agrees to maintain its tender. If that tenderer agrees to this without reservation, the contracting authority shall proceed to the award and the conclusion of the contract.
If the tenderer in question agrees to maintain its tender only on condition that it obtains a change to its tender, the award and the conclusion of the contract shall take place including the requested change, if the tenderer justifies the change on the basis of circumstances that have arisen after the final date and time for the submission of tenders and the tender thus changed remains the most economically advantageous.
If the tenderer in question does not agree to maintain its tender, or the requested change does not prove to be justified, or the changed tender does not remain the most economically advantageous, the contracting authority shall turn:
1° either successively, according to the ranking, to the other regular tenderers. In this case the second and third paragraphs shall also apply;
2° or simultaneously to all the other regular tenderers with the request to revise their tender, on the basis of the original conditions of the contract, in order subsequently to award and conclude the contract on the basis of the tender that has become the most economically advantageous. In order to be taken into account, the requested changes must be justified on the basis of circumstances that have arisen after the final date and time for the submission of tenders. The contracting authority shall also take into account the tender changed by application of the third paragraph, insofar as the justification given has been accepted.
Where the most economically advantageous tender is determined, in accordance with Article 81, § 2, first paragraph, 1°, of the Act, solely on the basis of price, the revision referred to in the fourth paragraph, 2°, may relate only to the tender price.
Amended byKB 2018-04-15/01, art. 41 (in force 28-04-2018)
Cross-references
Referred to by
Previous article
88 — The contract is concluded by the notification to the contractor of the approval…
Next article
90 — The contracting authority may use the negotiated procedure without prior…