Text of the consolidated version in force from 17 February 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 The contracting authority may use a competitive procedure with negotiation in the following cases:

1° with respect to works, supplies or services fulfilling one or more of the following criteria:

a) the needs of the contracting authority cannot be met without adaptation of readily available solutions;

b) they include design or innovative solutions;

c) the contract cannot be awarded without prior negotiations because of specific circumstances related to the nature, the complexity or the legal and financial make-up, or because of the risks attaching to them;

d) the technical specifications cannot be established with sufficient precision by the contracting authority with reference to a standard, European technical assessments, a common technical specification or a technical reference as referred to in Article 2, 45° to 48°;

e) access to the contract is reserved in accordance with Article 15 and the estimated amount of the contract, exclusive of value added tax, is lower than the threshold laid down for European publication;

f) the estimated amount of the contract, exclusive of value added tax, is lower than the amounts determined by the King;

2° with respect to works, supplies or services for which, in response to an open or restricted procedure, only irregular or unacceptable tenders were submitted.

In the case referred to in the first paragraph, under 2°, the contracting authority is not obliged to publish a contract notice if it admits to the procedure only all tenderers that satisfy the criteria referred to in Articles 67 to 78 and that, in the preceding open or restricted procedure, submitted tenders which complied with the formal requirements of the award procedure. If it does not admit all those tenderers to the procedure, the contracting authority shall be obliged to publish a contract notice.

Where the first procedure is not subject to mandatory European publication, the contracting authority may, however, in order to broaden competition, additionally consult economic operators which in its view are able to meet the selection requirements, irrespective of whether or not they submitted a regular tender, or submitted no tender at all, in the context of the first procedure. In such a case, the contracting authority is not obliged to publish a contract notice.

§ 2 In a competitive procedure with negotiation and without prejudice to § 1, second and third paragraphs, any economic operator may submit a request to participate in response to a contract notice by providing the information for selection requested by the contracting authority.

§ 3 The contracting authority shall identify in the procurement documents the subject-matter of the contract by describing its requirements and the required characteristics of the works, supplies or services and by laying down the award criteria. It shall also indicate which elements of the description define the minimum requirements to be met by all tenders.

The information provided shall be sufficiently precise to enable economic operators to identify the nature and scope of the contract and to decide whether to participate in the procedure.

The time limit for the receipt of requests to participate shall be at least thirty days, counted from the date of dispatch of the contract notice. The time limit for the receipt of initial tenders shall be at least thirty days, counted from the date of dispatch of the invitation. Article 37, §§ 3 to 5, applies.

§ 4 Only those economic operators invited to do so by the contracting authority following its assessment of the information provided may submit an initial tender. This shall serve as the basis for the subsequent negotiations. The contracting authority may, in accordance with Article 79, limit the number of candidates invited to participate in the procedure.

§ 5 With a view to improving their content, the contracting authority shall negotiate with tenderers the initial tenders and all subsequent tenders submitted by them, except for the final tenders within the meaning of § 8. The contracting authority may nevertheless award the contracts on the basis of the initial tenders without negotiation, if it has reserved the possibility to do so in the contract notice.

The minimum requirements and the award criteria shall not be subject to negotiation.

§ 6 During the negotiations, the contracting authority shall ensure the equal treatment of all tenderers. To that end, it shall not provide information in a discriminatory manner which may give some tenderers an advantage over others. It shall inform in writing all tenderers whose tenders have not been eliminated pursuant to § 7 of any changes to the technical specifications or other procurement documents, other than those setting out the minimum requirements. Following those changes, the contracting authority shall give tenderers sufficient time to modify and resubmit their tenders, where necessary.

In accordance with Article 13, the contracting authority shall not reveal to the other participants confidential information communicated by a candidate or tenderer participating in the negotiations without that person's written consent. Such consent shall not take the form of a general waiver but shall be given with reference to the intended communication of specific information.

§ 7 The competitive procedure with negotiation may take place in successive stages in order to reduce the number of tenders to be negotiated by applying the award criteria specified in the contract notice or another procurement document. The contracting authority shall indicate in the contract notice or another procurement document whether it will use that option.

§ 8 Where the contracting authority intends to conclude the negotiations, it shall inform the remaining tenderers and set a common deadline to submit any new or revised tenders. The contracting authority shall verify that the final tenders comply with the minimum requirements and with Article 66, § 1, evaluate the final tenders on the basis of the award criteria and award the contract pursuant to Articles 79 to 84.

Where the contracting authority has reserved in the contract notice the right not to conduct negotiations, and it makes use of that possibility, the initial tender shall accordingly be regarded as the final tender.

§ 9 The King may lay down the further additional procedural rules applicable to the competitive procedure with negotiation.

Cross-references

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.